16'x24' Buildingw/ Full LoftSentryBuildingsManufactured by Reynolds Building Systems, Inc.205 Arlington Drive Greenville, PA 16125 724-646
Step 8 Install 2nd Floor Loft BeamBeam5. Place the beam into the beampocket. Secure in place with16d sinkers.2x4 Wall Brace1. Cut (2) two 1-3/4"
Beam2x4 Tie Plate5. Tongue and groove flooring does not cover 48" width. Install a 1x4-8' white pine boardfiller after the last row of floor
SidewallLoft FloorPanel #7Panel #6Step 10 Install Front & Back Wall Trim1. Cut 1x4-10' trim boards to length for the front corners. Install t
Siding ExtendsBelow Bottom PlateStep 11 Assemble Rear Roof Gable ContinuedReapply SidingFront Wall8. Install the gable frames numbered 9 and 10 to the
2x4x83-3/4"2x4x82-1/4"2nd LayerEnd With Blue Mark4. Locate (4) four 2x4s that are 84-1/2" long and have an angle block attached to one
Step 13 Assemble Trusses1. Lay 2x6 truss parts inside the 2x4 blocks. One end of the 81-3/4" long 2x6 boards have a bluemark. Place these ends t
1-1/2"floor2x4 Tie Plate2x6 Truss Plate2x6 Truss PlateStep 14 Set Gables and 2x6 Truss Plate4. Layout 2x6 plate for trusses. Important: Startthe
2-1/2" Screw2x6 SoffitBlock1x3 Board2x6 TrussPlate2x6 Truss Plate2. Secure trusses to 2x6 truss plates with 2x6metal hangers. Nail metal hanger t
Building Tip: Ridge vent provides idealventilation, preventing heat or moisture fromdamaging your building or its contents.Ridge vent providesideal ve
1x6 Gable Trim1. Install 82-1/4" long 1x6 white pine trim boards at the top of the gable overhangs. Installthe end with the blue marking at the r
measurefrom hereWhen measurements are given for board length,it is from the longest side of the board.ToolListHammer & Phillips ScrewdriverFraming
Material Needed 25 bdl. roof shingles, 12 pcs. roof edge and 2 rolls felt paper.Packing List Richmond 16' Wide x 24' Barn KitQty. Qty.22 4 x
Stud SpacingXXXXXX8' - 0" PlatesNOTE: In westernstates all wall studsare 92-1/4" in length!Step 1 Assemble Rear Wall2. Install 92-5/8&q
16"16"Step 2 Assemble Front Door Wall2. Cut (2) two 7-1/2" x 48" long fillers fromOSB sheathing that was used to wrap thepallet. I
*83-3/8" When usingwestern wall studs.*LAPEdgeInstall SidingFlushStep 2 Assemble Front Door Wall ContinuedSiding Extends 3/4" Below PlateSid
6. Install (2) two full width siding panels.16"11-3/4"16"3. Install 92-5/8" wall studs between the top and bottom plates. Install
XXXX2. Install 92-5/8" wall studs between the top and bottom plates.11-3/4" SpaceNote: Position the panelso the 11-3/4" stud spacein at
Step 6 Assemble Right Sidewalls1. Repeat 4 and 5 to assemble the wall frames for the right sidewall.2. Positions the wall frame with the beam support
1. Set the left sidewall panels and the 96" long back wall panel. Secure the corner togetherwith 16d sinkers, (4) four nail per corner.2. Set the